Item 67
contract late itemJun 17, 2026
Description
Authorize Division of Parks and Recreation, Bureau of Trails to retroactively amend an existing contract agreement with HEB Engineers, Inc., North Conway, NH, for Engineering and Survey Services for two snowmobile bridge abutments and approaches on Corridor 19 snowmobile trail within the White Mountain National Forest in Chatham, NH by extending the completion date from December 31, 2025, to August 25, 2026, with no change to the price limitations of $137,811. Effective retroactive to December 31, 2025 upon G&C approval. The original contract was approved on February 8, 2023, Item #88, archived document . 100% Federal Funds
Amount
$137,811
$137,811
Department
DEPARTMENT OF NATURAL AND CULTURAL RESOURCES
Funding Source
100% Federal Funds
Documents (1)
Item_67.pdf
Open in new tab →