Description

Authorize to execute a sole source amendment to the contract with Gannett Fleming, Inc., d/b/a GFT Infrastructure, Inc., Camp Hill, PA, by increasing the contract by $2,920,464 from $5,743,406 to $8,663,870 for dam engineering services anticipated at Murphy Dam in Pittsburg, Newfound Dam in Bristol, and Hadley Falls Dam in Goffstown. Effective upon G&C approval through December 31, 2028. The original contract was approved by Governor and Council on October 19, 2022, item #72 archived document , amended on June 26, 2024, item #135 archived document , and amended on March 25, 2026, item #78 archived document . 37.7% Capital (General) Funds, 17.8% Federal Funds, 44.5% Aquatic Resource Mitigation (ARM) Funds

Amount
$8.7M
$2,920,464, $5,743,406, $8,663,870
Funding Source
37.7% Capital (General) Funds; 17.8% Federal Funds; 44.5% Aquatic Resource Mitigation (ARM) Funds